Contact UsContact Us

Huagou Piling Driving Machinery

Tel:0319 4891497

Director Jia:18603192304

Manager Yin:13247468123

Web:www.qianshuizuanji.com

Web:en.qianshuizuanji.com

Address: Located at the 50 meters south of Tian Jiu Tai Ke Courtyard, south side of Chunqiu Road, West side of 308 National Road, Xinhe County, Xingtai City

Through the watertightness test of the rig pipe, understand the rig pipe wall bearing

Through the watertightness test of the rig pipe, understand the rig pipe wall bearing

2019-11-18
second

1. Purpose of watertight test of rig conduit


Ensure that the technological process of the bridge pile foundation pouring pile operation does not affect the construction process.


2, requirements and methods


1) Make all drilling rig ducts strong, and the inner wall should be smooth, straight, smooth and free of local bumps. The inner diameter of each section of the catheter should be the same, and the deviation is not greater than ± 2mm.


2) Before using the drill rig duct and after a period of use, in addition to careful inspection of its specifications, quality and splicing structure, splicing, watertightness, and other tests are also required.


3) Connect the end of the rig's pipe with a sealing fastener. The catheter can be assembled in sections next to the borehole, and then assembled section by section when hoisting. Careful inspection should be carried out when assembling in sections, and severe deformation and wear must not be used.


4) Fill the assembled pile pipe first with 70% water, both ends are closed, and one end is welded to the air pipe joint. Enter the calculated wind pressure, and the pipe needs to be rolled several times. It will be qualified after 15 minutes without water leakage.


3. Calculation method of bearing pressure of drilling rig conduit


The water pressure in the watertight test of the concrete pipe of the cast-in-situ pile shall not be less than the pressure of 1.3 times the water depth in the wellbore. The water pressure during the pressure test shall not be less than the internal pressure Pmax that the wall of the pipe may bear. Pmax can be calculated as follows:


Pmax = 1.3 (ㄚ cHcmax- ㄚ wHw)


In the formula: Pmax——the internal pressure that the catheter wall may withstand, KPa;


ㄚ c——Concrete bulk density (with 24KN / m3), KN / m3;


CHcmax——the height of the concrete column in the duct, using the length of the duct, m;


ㄚ w——water or mud bulk density in the borehole, when the mud volume is greater than 12KN / m3, underwater concrete should not be poured, KN / m3;


Hw——water or mud depth in the borehole, m.


1K634G22-0.jpg

Label

Recent:

Related products

Related news

all rights reserved:Xinhe County Huagou Piling Driving Machinery factory 

Address: Located at the 50 meters south of Tian Jiu Tai Ke Courtyard, south side of Chunqiu Road, West side of 308 National Road, Xinhe County, Xingtai City

TEL:86-0319-4891497 Phone:18603192304 FAX:86-1324-7468123 Technical Support:ronglida.net.cn ICP:13016323-1 Business license

新河县华构桩工机械厂是专业生产:正反循环钻机,正循环钻机,灌注桩钻机,车载钻机,步履式打桩机,液压打桩机,反循环钻机厂家

Online consultation